Call Creek

Call Creek

Call Creek Location – West Jefferson, NC Completed – 2019 The project involved 3,220 feet of stream work along Call Creek. There was also 425 feet of stream work along a tributary to Call Creek. Bankfull benches were constructed to achieve proper stream...
Brewbaker Sorenson

Brewbaker Sorenson

Brewbaker sorenson Location – Longmont, Colorado Completed – 2019 The restoration of Left-Hand Creek was achieved by creating a pattern, dimension, and profile that was more appropriate to the valley type and stream type. The design was intended to give...
Boulder Creek Restoration

Boulder Creek Restoration

Boulder creek restoration Location – Boulder, Colorado Completed – 2017 The project included implementing a new southern channel totaling 2,500 ft of channel. Project goals included improved water quality, sediment transport, fish passage, in-stream...